Method for allocation of loading and unloading equipment in container rail-water intermodal hub
-
摘要:
为提高集装箱铁水联运枢纽装卸设备配置效率并降低集卡走行碳排放,本文考虑在“铁-水”直取与“铁-堆场-水”混合装卸模式下箱流与车船到达时空特性,构建了多目标组合优化模型。以设备运营成本、车船周转时间、集卡走行碳排放为优化目标,采用分区域集卡动态分配策略,引入时间离散区段化设备分配机制,动态决策了岸桥、铁路装卸区轨道吊、堆场轮胎吊及集卡的配置数量;基于时段分配规则的遗传算法求解模型,结合某铁水联运枢纽24 h运营数据进行验证。研究结果表明:对于原算例,在车船装卸时间重叠时,车船直取比例达82%,岸桥、铁路装卸区轨道吊与堆场轮胎吊的设备利用率提升了15%~20%,其中出口箱区、铁路进口箱区的轮胎吊作业量分别下降了15%、23%,证明车船直取是铁水联运转运的优选方式,可以显著提升枢纽设备的利用率,且铁路进口箱区堆场轮胎吊受直取能力影响显著;当限制枢纽直取区域内集卡配置量由8台减为2~4台时,总成本上升了1.2%~2.8%,集卡走行碳排放增加了16%,表明总成本与碳排放均对直取能力较为敏感;在装卸规模较大即5船4列时,设备运营成本占总成本的84.12%,当装卸规模减小至1船1列时,设备成本占比升至87.8%,表明动态设备分配机制在较大规模场景下能更有效地协调设备资源;所提算法与MATLAB整数线性规划求解器直接求解相比,枢纽运营总成本降低了19.1%;相较于标准遗传算法,平均求解时间缩短了33.5%,平均解质量提升了37.62%,表明本文算法稳定性与求解精度更好。研究结果可为铁水联运枢纽设备配置提供兼顾效率与环境友好的决策方法,通过动态分配设备数量,提升车船直取能力,减少堆场堆存量。
Abstract:To improve the efficiency of loading and unloading equipment allocation in rail-water intermodal transport container terminals and to reduce carbon emissions generated by container truck operations, a multi-objective combinatorial optimization model was developed considering the spatiotemporal characteristics of container flows and the rail-ship arrival under a hybrid handling mode of rail-water direct transfer and rail-yard-water operation. The optimization objectives were to minimize equipment operating costs, the turnaround times of trains and ships, and carbon emissions from container truck movements. A dynamic zone-based allocation strategy was proposed for container trucks. A discrete time-period equipment allocation mechanism was also introduced. The allocation numbers of quay cranes, rail-mounted gantry cranes, rubber tyred gantry cranes, and container trucks were dynamically determined. A genetic algorithm based on time-period allocation rules was designed to solve the model. The model was validated using 24-hour operational data from a rail-water intermodal transport container terminal. The results indicate that, in the original case, when the loading and unloading time windows of trains and ships overlap, the proportion of rail-ship direct transfer reaches 82%, the utilization rates of quay cranes, rail-mounted gantry cranes, and rubber tyred gantry cranes increase by 15%-20%, and the workload of rubber tyred gantry cranes in the export container yard and railway import container yard decreases by 15% and 23%, respectively. It proves that rail-ship direct transfer is the preferred transshipment mode for rail-water intermodal transport, which can significantly improve the utilization rate of terminal handling equipment, with significant impact of direct transfer capacity on the rubber tyred gantry cranes in railway import container yards. When the number of container trucks allocated to the direct-transfer zone reduces from 8 to 2-4 units, the total cost increases by 1.2%-2.8% and carbon emissions from container truck movements rise by approximately 16%, which indicates that both total cost and carbon emissions are highly sensitive to direct transfer capacity. Furthermore, under a large-scale handling scenario involving 5 ships and 4 trains, equipment operating costs account for 84.12% of the total cost, whereas this proportion increases to 87.8% when the handling scale is reduced to 1 ship and 1 train. This suggests that the proposed dynamic equipment allocation mechanism is more effective in coordinating equipment resources under larger-scale operational conditions. Compared with directly solving the model using the MATLAB integer linear programming solver, the proposed algorithm lowers the total operating cost of the terminal by 19.1%. Compared with the standard genetic algorithm, it shortens the average solution time by 33.5% and improves the average solution quality by 37.62%, which indicates its superior stability and solution accuracy. An efficiency-oriented and environmentally friendly decision-making approach can be provided for equipment configuration in rail-water intermodal transport container terminals. By dynamically allocating equipment quantities, the rail-ship direct transfer capability can be enhanced and yard congestion and storage pressure can be alleviated.
-
表 1 班轮信息
Table 1. Liner information
班轮序号 到港时间 离港时间 集装箱量/TEU 方向1 方向2 方向3 方向4 方向5 1 2025-01-22 12:05 2025-01-23 01:05 92 139 57 23 44 2 2025-01-22 14:30 2025-01-23 03:30 82 135 102 34 20 3 2025-01-22 22:00 2025-01-23 04:00 90 56 44 12 33 4 2025-01-23 01:00 2025-01-23 06:30 166 52 47 18 54 5 2025-01-23 04:30 2025-01-23 11:00 62 55 161 34 48 表 2 班列信息
Table 2. Train information
班列序号 到港时间 离港时间 集装箱量/TEU 方向1 方向2 方向3 方向4 方向5 1 2025-01-22 14:00 2025-01-22 17:00 33 10 0 45 34 2 2025-01-22 16:00 2025-01-22 19:00 22 38 0 18 37 3 2025-01-23 02:00 2025-01-23 05:00 32 39 0 22 50 4 2025-01-23 06:00 2025-01-23 09:00 57 45 0 29 58 表 3 外集卡信息
Table 3. External container truck information
时段序号 集装箱量/TEU 时段序号 集装箱量/TEU 方向1 方向2 方向3 方向1 方向2 方向3 1 12 12 19 13 14 22 24 2 18 8 17 14 7 8 13 3 25 8 15 15 22 15 6 4 11 20 19 16 13 10 13 5 18 12 14 17 20 9 11 6 25 8 22 18 14 5 25 7 10 12 19 19 8 7 22 8 13 10 17 20 9 15 12 9 7 9 23 21 24 24 16 10 27 10 11 22 10 10 25 11 17 10 22 23 16 10 13 12 27 21 14 24 21 11 19 表 4 堆场原始箱量
Table 4. Original container volume in the yard
TEU 箱流方向 方向1 方向2 方向3 方向4 方向5 对应堆场箱量 14 19 22 7 20 表 5 布局信息
Table 5. Layout information
属性 数值 水平方向的箱区个数 10 单个箱区长度/m 130 堆场宽度/m 220 堆场边缘到码头前沿的距离/m 200 堆场边缘到铁路装卸线的距离/m 100 内集卡在区域1平均走行距离/m 1 927 内集卡在区域2平均走行距离/m 1 727 内集卡在区域3平均走行距离/m 2 041 表 6 装卸区域占用费用
Table 6. Occupation fees of loading and unloading areas
元·h-1 属性 数值 船舶停泊费率 978.5 铁路装卸线占用费率 175.2 属性 岸桥 场桥 轨道吊 设备总量/台 6 12 5 同时段最大允许配置数量/台 3 4 3 每时段花费成本/元 735 600 700 单位时段实际装卸箱数/(TEU·h-1) 25 14 20 设备利用率 0.8 0.9 0.8 表 8 各区域内集卡装卸信息
Table 8. Internal container truck loading and unloading information within each region
属性 区域1 区域2 区域3 内集卡平均走行距离/m 1 927 1 727 2 041 最大允许配置数/台 10 8 8 等待时长/min 2 2 1 装卸/对集装箱所需时长/min 7.5 6.9 6.8 单位时段可装卸箱数/(TEU·h-1) 15 17 17 单位时段碳排放所需碳税/(元·h-1) 9.2 10.4 10.4 单位时段装卸成本/(元·h-1) 217.5 246.5 246.5 表 9 各运输单元的装卸时间窗
Table 9. Loading and unloading time windows for each transportation unit
运输工具 序号 开始装卸时段 结束装卸时段 最晚结束装卸时段 船舶 V1 1 9 14 V2 3 11 16 V3 11 15 17 V4 14 19 19 V5 17 24 24 列车 K1 3 5 6 K2 5 8 8 K3 15 18 18 K4 19 22 22 表 10 船舶与列车在各时段被分配的起重设备数量
Table 10. Number of cranes allocated to ships and trains at each time period
时段序号 不同运输工具被分配的起重设备数量/台 V1 V2 V3 V4 V5 K1 K2 K3 K4 1 1 2 3 3 3 3 2 4 2 3 2 5 2 3 2 6 1 1 1 7 2 8 1 1 3 9 1 3 10 2 11 2 1 12 2 13 3 14 2 2 15 2 3 1 16 3 3 17 3 1 3 18 2 2 1 19 2 3 2 20 3 3 21 2 2 22 2 3 23 2 24 1 表 11 箱区与区域在各时段被分配的起重设备和集卡数量
Table 11. Number of cranes or container trucks allocated to the container block and region at each time period
时段序号 箱区轮胎吊分配数量/台 集卡走行区集卡分配数量/台 箱区1 箱区2 箱区3 箱区4 箱区5 区域1 区域2 区域3 1 2 4 3 1 2 2 2 4 3 3 5 3 3 3 3 3 8 2 2 4 3 4 2 5 6 5 4 3 1 2 3 4 6 3 3 1 4 1 1 7 1 3 2 3 8 4 3 3 3 4 9 4 4 2 6 10 2 3 4 4 11 3 2 4 5 12 4 2 1 4 13 3 3 2 1 4 14 3 3 4 1 7 15 4 4 2 6 1 2 16 4 2 2 1 3 5 17 4 2 3 5 1 5 18 4 1 1 2 1 3 19 4 4 3 7 3 20 3 2 4 5 1 3 21 4 2 3 3 3 22 3 2 4 3 4 23 2 1 4 3 24 2 1 3 2 表 12 不同装卸规模算例的信息及计算结果
Table 12. Information and calculation results for cases with different handling scales
装卸规模 总任务箱量/TEU 总成本/元 设备装卸成本/元 泊位及装卸线占用成本/元 碳排放成本/元 箱均成本/元 5船4车(原算例) 1 660 55 835.60 46 971.0 7 972.8 891.8 33.64 3船3车 1 089 36 349.13 31 291.3 4 460.1 597.7 33.38 1船1车 573 19 100.20 16 769.3 2 062.1 268.7 33.33 表 13 算法求解总成本的性能对比
Table 13. Performance comparison of algorithms for solving total cost cost
性能指标 标准遗传算法 本文改进的遗传算法 最优总成本/元 55 835.6 55 835.6 平均求解时间/s 45.20 30.04 平均总成本/元 91 104.08 56 830.71 标准差/元 12 450.68 7 832.88 中位数/元 92 400.28 57 084.68 最差解/元 112 300.41 68 920.39 -
[1] JIANG M X, WU G X, ZHENG J P, et al. Container terminal berth-quay crane capacity planning based on Markov chain[J]. Promet-Traffic & Transportation, 2021, 33(2): 267-281. [2] NEHME N, MADDAH B, KAYSI I A. An integrated multi-ship crane allocation in Beirut port container terminal[J]. Operational Research, 2021, 21(3): 1743-1761. doi: 10.1007/s12351-019-00539-4 [3] TAN Z Y, ZHANG Q, YUAN Y, et al. A decision method on yard cranes transformation and deployment in green ports[J]. International Transactions in Operational Research, 2022, 29(1): 323-346. doi: 10.1111/itor.13027 [4] DING Y, YANG Y, HEILIG L, et al. Deployment and retrofit strategy for rubber-tyred gantry cranes considering carbon emissions[J]. Computers & Industrial Engineering, 2021, 161: 107645. [5] LIN S M, ZHEN L, WANG W C. Planning low carbon oriented retrofit of diesel-driven cranes to electric-driven cranes in container yards[J]. Computers & Industrial Engineering, 2022, 173: 108681. [6] GHAREHGOZLI A, ZAERPOUR N, LI K P. Optimizing the number of deployed yard cranes in a container terminal[J]. INFOR: Information Systems and Operational Research, 2023, 61(1): 86-103. doi: 10.1080/03155986.2022.2106713 [7] MA M Z, ZHAO W T, FAN H M, et al. Collaborative optimization of yard crane deployment and inbound truck arrivals with vessel-dependent time windows[J]. Journal of Marine Science and Engineering, 2022, 10(11): 1650. doi: 10.3390/jmse10111650 [8] ABOU KASM O, DIABAT A, CHOW J Y J. Simultaneous operation of next-generation and traditional quay cranes at container terminals[J]. European Journal of Operational Research, 2023, 308(3): 1110-1125. doi: 10.1016/j.ejor.2022.10.035 [9] 彭云, 李相达, 王文渊, 等. 绿色集装箱港口节能减排策略综述[J]. 交通运输工程学报, 2022, 22(4): 28-46. doi: 10.19818/j.cnki.1671-1637.2022.04.003PENG Yun, LI Xiang-da, WANG Wen-yuan, et al. Review on energy saving and emission reduction strategies of green container ports[J]. Journal of Traffic and Transportation Engineering, 2022, 22(4): 28-46. doi: 10.19818/j.cnki.1671-1637.2022.04.003 [10] GHAREHGOZLI A H, DE KOSTER R, JANSEN R. Collaborative solutions for inter terminal transport[J]. International Journal of Production Research, 2017, 55(21): 6527-6546. doi: 10.1080/00207543.2016.1262564 [11] STOJAKOVIĆ M, TWRDY E. Determining the optimal number of yard trucks in smaller container terminals[J]. European Transport Research Review, 2021, 13(1): 22. doi: 10.1186/s12544-021-00482-6 [12] ZHANG X J, ZENG Q C, YANG Z Z. Modeling the mixed storage strategy for quay crane double cycling in container terminals[J]. Transportation Research Part E: Logistics and Transportation Review, 2016, 94: 171-187. doi: 10.1016/j.tre.2016.08.002 [13] ANVARI B, ZIAKOPOULOS A, MORLEY J, et al. Comparison of Fleet size determination models for horizontal transportation of shipping containers using automated straddle carriers[M]. Handbook of Terminal Planning. Cham: Springer, 2020. [14] URIBE-MARTES C J, RIVERA-RESTREPO D X, FILIPPO A B, et al. Simulation model of internal transportation at a container terminal to determine the number of vehicles required[C]// Springer. Inventive Computation Technologies. Cham: Springer, 2020: 912-919. [15] CHARGUI K, ZOUADI T, FALLAHI AEL, et al. Berth and quay crane allocation and scheduling with worker performance variability and yard truck deployment in container terminals[J]. Transportation Research Part E: Logistics and Transportation Review, 2021, 154: 102449. doi: 10.1016/j.tre.2021.102449 [16] ZHANG Q, WANG S, ZHEN L. Yard truck retrofitting and deployment for hazardous material transportation in green ports[J]. Annals of Operations Research, 2024, 343(3): 981-1012. [17] CASTILLA-RODRÍGUEZ I, EXPÓSITO-IZQUIERDO C, MELIÁN-BATISTA B, et al. Simulation-optimization for the management of the transshipment operations at maritime container terminals[J]. Expert Systems with Applications, 2020, 139: 112852. doi: 10.1016/j.eswa.2019.112852 [18] ZENGIN A, HAMDOON W. Simulation of cargo unloading problem: A case study on estimating the optimal number of trucks and cranes[J]. Sakarya University Journal of Computer and Information Sciences, 2022, 5(3): 404-414. doi: 10.35377/saucis...1173791 [19] MAHPOUR A, NAZIFI A, MOHAMMADIAN AMIRI A. Development of optimization model to reduce unloading and loading time at berth in container ports[J]. Iranian Journal of Science and Technology, Transactions of Civil Engineering, 2021, 45(4): 2831-2840. doi: 10.1007/s40996-021-00590-2 [20] LI J J, YAN L X, XU B W. Research on multi-equipment cluster scheduling of U-shaped automated terminal yard and railway yard[J]. Journal of Marine Science and Engineering, 2023, 11(2): 417. doi: 10.3390/jmse11020417 [21] 虞楠, 郭紫莹. 新形势下我国港口铁水联运发展对策探讨[J]. 铁道运输与经济, 2021, 43(10): 35-41.YU Nan, GUO Zi-ying. Development of rail-water intermodal transport of China's ports under the new situation[J]. Railway Transport and Economy, 2021, 43(10): 35-41. [22] 刘勇, 朱晓宁, 朱颂雅, 等. 铁水联运港站的铁路作业区轨道门吊优化配置[J]. 武汉理工大学学报(交通科学与工程版), 2014, 38(5): 1135-1139.LIU Yong, ZHU Xiao-ning, ZHU Song-ya, et al. Allocation optimization model of the rail-mounted gantry crane in railway area by rail-water intermodal container transport[J]. Journal of Wuhan University of Technology (Transportation Science & Engineering), 2014, 38(5): 1135-1139. [23] YAN B C, XU M. Container flow template planning in seaport railway terminal with on-dock rails[J]. Maritime Policy & Management, 2023, 50(4): 538-561. [24] LI S Y, HAN X L. Collaborative scheduling of rail-mounted gantry crane and container truck in hybrid operation mode of rail-water intermodal terminal[J]. Journal of Computer Applications, 2021, 41(05): 1506-1513. [25] WANG N Y, SHEN M R, WEI Y C. Research on handling equipment allocation of rail-sea intermodal transportation in container terminals[C]//IEEE. 2020 IEEE 5th International Conference on Intelligent Transportation Engineering (ICITE). New York: IEEE, 2020: 530-535. [26] LI W F, WU Z T, YANG P F, et al. Collaborative scheduling optimization of equipment in multimodal transport harbor considering hybrid operation mode of "train-yard-vessel" and "train-vessel"[C]//IEEE. 2022 IEEE 18th International Conference on Automation Science and Engineering (CASE). New York: IEEE, 2022: 86-91. [27] YANG Y S, HE S, SUN S. Research on the cooperative scheduling of ARMGs and AGVs in a sea-rail automated container terminal under the rail-in-port model[J]. Journal of Marine Science and Engineering, 2023, 11(3): 557. doi: 10.3390/jmse11030557 [28] 刘道宽, 卢勇利, 沈学明, 等. 我国铁水联运港口作业区布局优化研究[J]. 铁道运输与经济, 2020, 42(5): 30-37.LIU Dao-kuan, LU Yong-li, SHEN Xue-ming, et al. A study on the optimization of the operation area of railway-water intermodal transport port in China[J]. Railway Transport and Economy, 2020, 42(5): 30-37. [29] 杨忠振, 张尔卓, 杜怡颖, 等. 基于文献计量的多式联运物流工程研究综述[J]. 交通运输工程学报, 2026, 26(2): 1-23. doi: 10.19818/j.cnki.1671-1637.2026.071YANG Zhong-zhen, ZHANG Er-zhuo, DU Yi-ying, et al. Review of multimodal transport logistics engineering based on bibliometrics[J]. Journal of Traffic and Transportation Engineering, 2026, 26(2): 1-23. doi: 10.19818/j.cnki.1671-1637.2026.071 [30] 周磊磊, 梁承姬, 胡筱渊. 不确定干扰约束下外集卡提箱策略[J]. 计算机应用, 2020, 40(3): 891-896.ZHOU Lei-lei, LIANG Cheng-ji, HU Xiao-yuan. Delivery truck strategy under uncertain interference constraints[J]. Journal of Computer Applications, 2020, 40(3): 891-896. [31] ZHANG X J, GU Y, YANG Y Q, et al. Comparing the efficiency of two types of yard layout in container terminals[J]. Sustainability, 2023, 15(9): 7195. doi: 10.3390/su15097195 [32] LAU H Y K, ZHAO Y. Integrated scheduling of handling equipment at automated container terminals[J]. International Journal of Production Economics, 2008, 112(2): 665-682. doi: 10.1016/j.ijpe.2007.05.015 [33] 聂煜阳. "列车: 船舶"直取模式下的集装箱港口作业设备调度优化研究[D]. 北京: 北京交通大学, 2019: 87-89.NIE Yu-yang. Research on the optimization of container port operation equipment scheduling under "train-ship" direct access mode[D]. Beijing: Beijing Jiaotong University, 2019: 87-89. [34] 郭婵婵. 考虑能耗的集装箱码头核心资源调度研究[D]. 大连: 大连海事大学, 2014: 38-40.GUO Chan-chan. Research on container terminal core resource scheduling[D]. Dalian: Dalian Maritime University, 2014: 38-40. [35] 张欣, 毛婧. 基于多层网络的中欧集装箱海铁联运系统韧性评估[J]. 交通运输工程学报, 2026, 26(9): 233-245.ZHANG Xin, MAO Jing. Multilayer network-based resilience evaluation for China-Europe container sea-rail intermodal transport systems[J]. Journal of Traffic and Transportation Engineering, 2026, 26(9): 233-245. -
下载: