摘要: 为了做到碾压机械配置合理有效, 分析了常用碾压机械的性能和沥青道面铺筑的特点, 提出了从沥青拌和厂的产量、摊铺机的生产效率和摊铺厚度、施工气候条件等因素综合选择并确定碾压机械的类型与型号。结合机场跑道沥青铺筑实践, 对碾压作业段长度、碾压速度与压实度的关系、压路机有效工作时间系数等影响碾压机械配置的因素进行了系统试验研究, 提出了计算压路机生产率的方法, 并给出了从压路机的轮宽、碾压遍数、有效作业段长度、摊铺机的速度及宽度等参数合理配置碾压机械的方法与计算公式。通过三个机场工程的实际应用, 计算结果表明碾压机械配置效果良好。Abstract: Taking into account of such factors as the output of asphalt mix machines, production efficiency and paving depth of pavers and weather conditions, this paper analyzed the perform-ances of common rolling compaction machines and features of asphalt pavement construction to determine the types and model of machines. After a systematic experiment on the factors affect-ing the rolling compaction machine configuration such as the rolling compaction operation section length, the relation between rolling speed and compaction degree, roller grader effective working time coefficient, the paper put forward the method to calculate rollers' production rate and the method and formula of rationally disposing rolling compaction machines. The applied result proves this methods are effective.
-
Key words:
- airport engineering /
- asphalt pavement building /
- compaction machines /
- disposing methods
-
表 1 碾压作业程序与压路机类型选择
Table 1. Operation order and choice of roller grader type
表 2 有效压实时间与碾压作业段长度
Table 2. Rational rolling compaction time and operation sections'length
表 3 不同碾压速度、碾压遍数与压实度的关系
Table 3. Different rolling compaction speed, time and compaction degree
表 4 压路机碾压速度
Table 4. Rolling compaction speed of roller graders
表 5 碾压作业段长度与有效工作时间系数
Table 5. Rolling compaction operation sections'length and effective working time coefficient
表 6 压路机型号与碾压遍数
Table 6. Roller grader model and rolling compaction times
-
[1] 何曾亮. 军用机场跑道加铺沥青层的技术研究[D]. 西安: 空军工程大学, 2002. [2] 狄赞容. 施工机械概论[M]. 北京: 人民交通出版社, 1996. [3] MH 5011-1999, 民用机场沥青混凝土道面施工技术规范[S]. [4] JTJ 032-94, 公路沥青路面施工技术规范[S]. [5] 李长来. 沥青路面压实机械的选型与组合[J]. 公路, 1998, 43(12): 38-39. https://www.cnki.com.cn/Article/CJFDTOTAL-GLGL199812009.htmLI Chang-lai. Selection and combination of asphalt pavement rolling machines model[J]. Highway, 1998, 43(12): 38-39. (in Chinese) https://www.cnki.com.cn/Article/CJFDTOTAL-GLGL199812009.htm [6] 黄灿华. 机场施工与管理[M]. 北京: 人民交通出版社, 2002. [7] SHI Bao-Hua, WANG Sheng. Quality control of asphalt con-crete covering layer for cement concrete pavement[A]. 3th International Conference on Road Airfield Pavement Technology[C]. Beijing: People's Communications Publishing House, 1998.