摘要: 阐述了公路旧桥加固效果后评价的基本概念和内容体系, 在传统成功度评价法的基础上, 提出了成功度综合评价法用以评价桥梁加固后的综合效果。该方法应用层次分析法建立桥梁加固项目成功度综合评价指标体系; 采用德尔菲评分法确定评价指标集, 并根据指标类型的不同对其进行优化处理, 得到成功度综合评价矩阵; 对模糊数学理论的矩阵算子进行拓广, 建立了既全面考虑又兼顾重点的成功度综合评价计算模型。算例中双曲拱桥加固后项目成功度的计算结果为0 46, 成功度综合评价结论为“部分成功”, 与实际相符, 这说明成功度综合评价方法可综合专家的模糊评价信息, 能对桥梁加固效果作出合理的定性评价。Abstract: In order to evaluate bridge strengthening effectiveness, the paper put forward the conception and content system of post-evaluation of bridge strengthening effectiveness, based on the conventional success-degree evaluation method, set up the comprehensive success-degree evaluation model of bridge strengthening effectiveness. In the model, the evaluating indices system of success-degree for bridge strengthening was established by analytic hierarchy process, the indexing set of evaluating indicators was determined with the merits of Delphi method, and it was optimized according to the different types of indicators, hence comprehensive appraisal matrix was formed, the matrix operator of fuzzy theory was improved. Computation result of bridge evaluation is 0.46, comprehensive evaluation is part success, which accords with the bridge real situation, the model is feasible.
-
表 1 评价指标的标准分值
Table 1. Numeric values of evaluating indicators
等级 5 4 3 2 1 评语集 完全成功 成功 部分成功 不成功 失败 指标值 9 7 5 3 1 表 2 专家评价结果
Table 2. Evaluation result of experts
评价指标 专家评分值 甲 乙 丙 u11 7 7 5 u21 5 6 6 u22 5 5 4 u23 7 5 6 u24 7 6 5 u25 5 7 6 u26 4 5 5 u27 5 5 4 u31 7 5 6 u32 6 6 5 u33 5 7 6 u34 5 4 5 u41 7 5 6 u42 8 7 7 u51 5 5 4 u52 5 5 4 u61 5 5 6 u62 7 7 6 -
[1] 张三力. 项目后评价[M]. 北京: 清华大学出版社, 2001. [2] 景宏君, 延西利. 公路技术评价方法[J]. 交通运输工程学报, 2001, 1(4): 41-43. http://transport.chd.edu.cn/article/id/200104009JING Hong-jun, YAN Xi-li. On highway technique evaluation method[J]. Journal of Traffic and Transportation Engineering, 2001, 1(4): 41-43. (in Chinese) http://transport.chd.edu.cn/article/id/200104009 [3] 赵维双, 常伟. 技术扩散效果的模糊综合评价模型研究[J]. 沈阳工业学院学报, 2001, 20(1): 77-81. https://www.cnki.com.cn/Article/CJFDTOTAL-SGXY200101016.htmZHAO Wei-shuang, CHANG Wei. The study of fuzzy comprehensive evaluation model for the effect of technology spread [J]. Journal of Shenyang Institute of Technology, 2001, 20(1): 77-81. (in Chinese) https://www.cnki.com.cn/Article/CJFDTOTAL-SGXY200101016.htm [4] 吕滨. 投资性贷款项目后评估成功度评价的模糊数学方法[J]. 决策借鉴, 1996, 10(5): 42-44. https://www.cnki.com.cn/Article/CJFDTOTAL-JCJJ605.019.htmLU Bin. Fuzzing mathematics method for success-degree evaluation of post-evaluation of investment loan items[J]. Policy Making Reference, 1996, 10(5): 42-44. (in Chinese) https://www.cnki.com.cn/Article/CJFDTOTAL-JCJJ605.019.htm [5] 郑继光, 王潮海, 孙福申, 等. 混凝土桥梁结构工后评价及其方法[J]. 东北公路, 2002, 25(2): 69-71. https://www.cnki.com.cn/Article/CJFDTOTAL-DBGL200202026.htmZHENG Ji-guang, WANG Chao-hai, SUN Fu-shen, et al. Late evaluation and evaluated method of concrete bridge structure [J]. Northeastern Highway, 2002, 25(2): 69-71. (in Chinese) https://www.cnki.com.cn/Article/CJFDTOTAL-DBGL200202026.htm [6] 武同乐. 桥梁加固后评价方法研究[D]. 西安: 长安大学, 2004. [7] 谌润水, 胡钊芳, 帅长斌. 公路旧桥加固技术与实例[M]. 北京: 人民交通出版社, 2002. [8] 徐岳, 武同乐. 桥梁加固工程生命周期成本横向对比分析[J]. 长安大学学报(自然科学版), 2004, 24(3): 30-34. https://www.cnki.com.cn/Article/CJFDTOTAL-XAGL200403008.htmXU Yue, WU Tong-le. Life-cycle cost comparative analysis of bridges strengthening[J]. Journal of Chang'an University(Natural Science Edition), 2004, 24(3): 30-34. (in Chinese) https://www.cnki.com.cn/Article/CJFDTOTAL-XAGL200403008.htm