摘要: 应用运行列车组的方法, 研究了高速列车的运行过程, 针对同类型运行列车组、高中运行列车组的易调整性以及中高运行列车组的调整难度与各种运行列车组的晚点情况提出了相应的调整规则。仿真结果表明运行列车组能够更好地反应高速列车的晚点情况, 给出的调整规则对高速列车的运行调整是可行的。Abstract: This paper studied the operation process of the high-speed train by applying operation train group. It was pointed out that the operation adjustment was easy for the same kind operation train group and high-medium speed operation train group, difficult for medium-high speed operation train group. For all kinds of operation train group, this paper presented corresponding adjustment rules. Simulation results indicate that operation train group is a validate method for studying the high-speed train operating process, and the adjustment rules are feasible.
-
Key words:
- high-speed railway /
- existing railway /
- operation adjustment /
- operation train group
-
表 1 仿真结果
Table 1. Simulation result
实验 平均晚点时间/s 到站晚点列车数 走备用线列车数 停运列车数 1 8 10 0 0 2 23 8 1 0 3 41 9 3 1 -
[1] 李琴. 京沪高速铁路综合调度系统技术条件的研究[R]. 北京: 铁道科学研究院, 2003. [2] 何邦模. 高速铁路综合调度系统用户需求研究报告[R]. 北京: 铁道科学研究院, 2002. [3] NIE Lei, ZHANG Xing-chen. Study on the strategy of train operation adjustment on high speed railway[J]. Journal of the China Railway Society, 2001, 23(4): 1-6. (in Chinese) [4] TANG Qi-zhi, SHI Hao. Discussion of the train operation adjustment problem on the Jing-Hu high speed railway[J]. China Railway, 2001, 12(1): 37-38. (in Chinese) [5] WU Wen-lin. Computer driving command system[J]. Railway Communication Signal, 1994, 30(9): 34-36. (in Chinese) [6] PU Yun, ZHANG Dian-ye. Study on Chinese train operation dispatch manage intelligent systems[J]. World Science-Technology Research and Development, 2000, 21(3): 45-47. (in Chinese) [7] PIAO Ai-hua, HU An-zhou. Study of the train operation organizing on Chinese high speed railway[J]. Journal of the China Railway Society, 1996, 18(3): 105-110. (in Chinese) [8] 杨浩, 何世伟. 铁路运输组织学[M]. 北京: 中国铁道出版社, 2001.